Also written as SPI
SPI measures progress in dollars, not time. It says nothing about which activities are late, and late work off the critical path can look the same as late work on it.
Near the end of a project SPI drifts back towards 1.0 even when the finish date has slipped, because eventually all planned value is earned. Check float and the critical path alongside it.
SPI = EV ÷ PV
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). SPI = 4.8 ÷ 5.2 = 0.92: about 92% of the planned work has been done.