What is CPI (cost performance index)?

    The cost performance index shows how much value of work is earned for each dollar spent. Below 1.0 means the work is costing more than budgeted.

    Also written as CPI

    CPI is one of the most watched figures in earned value because it tends to be stable once a project is part way through. A CPI that is poor early rarely recovers on its own.

    Because CPI relies on both progress measurement and cost cut-off, check both before acting on a sudden change.

    Formula

    CPI = EV ÷ AC

    Worked example

    A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). CPI = 4.8 ÷ 4.55 = 1.05: each dollar spent has earned about $1.05 of budgeted work.