What is EV (earned value)?

    Earned value is the budgeted value of the work actually completed by a given date. It measures progress in dollars, so different kinds of work can be added together.

    Also written as EV

    EV is calculated by applying measured percent complete to each item's budget. It is only as good as the progress measurement behind it: estimated or optimistic percentages produce optimistic EV.

    Comparing EV with planned value shows schedule performance; comparing it with actual cost shows cost performance.

    Formula

    EV = percent complete × budget, summed across the work

    Worked example

    A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). EV is $4.8 million.