Activities with zero or negative total float are on the critical path. Negative float means the schedule can't meet a required date as it stands.
Float is shared along a chain of activities, so using it early leaves less for the work that follows.
Related terms
Critical path
The longest chain of dependent activities through a schedule.
Baseline
An approved snapshot of the schedule, budget or scope, kept so actual performance can be compared against the plan.
Look-ahead schedule
A short-term, detailed view of the next few weeks of work, taken from the main schedule and used to plan and clear constraints.