Also written as TCPI
Compare TCPI with the current CPI. If the project needs to perform far better than it has so far to stay on budget, the budget is unlikely to hold.
TCPI = (BAC − EV) ÷ (BAC − AC)
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). TCPI = ($12m − $4.8m) ÷ ($12m − $4.55m) = 0.97, below the current CPI of 1.05, so the budget looks achievable.