Also written as VAC
VAC is only as reliable as the estimate at completion it is based on.
VAC = BAC − EAC
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). VAC = $12m − $11.375m = +$625,000, a forecast underrun.
Related terms
Estimate at completion
EACThe forecast total cost of the work when it's finished, based on performance so far and what's left to do.
Budget at completion
BACThe total approved budget for the work being measured.
Cost variance
CVThe difference between the value of work completed and what it actually cost.