Also written as BAC
BAC normally comes from the approved cost baseline. It excludes contingency that hasn't been allocated to work, so a project's BAC and its total approved funding are often different numbers.
When approved changes add or remove scope, the BAC changes with them. Comparing performance against an out-of-date BAC makes every index that depends on it misleading.
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). BAC is $12 million.