What is BAC (budget at completion)?

    Budget at completion is the total approved budget for the work being measured. It is the figure every earned value calculation is measured against.

    Also written as BAC

    BAC normally comes from the approved cost baseline. It excludes contingency that hasn't been allocated to work, so a project's BAC and its total approved funding are often different numbers.

    When approved changes add or remove scope, the BAC changes with them. Comparing performance against an out-of-date BAC makes every index that depends on it misleading.

    Worked example

    A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). BAC is $12 million.