Also written as CV
CV is the dollar version of the cost performance index. It is easier to explain in a report, while CPI is easier to compare between projects of different sizes.
Formula
CV = EV − AC
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). CV = $4.8m − $4.55m = +$250,000, an underrun so far.