Also written as SV
SV is expressed in dollars, not days. A $400,000 schedule variance tells you how much planned work hasn't been done, not how late the project will finish.
SV = EV − PV
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). SV = $4.8m − $5.2m = −$400,000.
Related terms
Schedule performance index
SPICompares the value of work completed with the value planned.
Cost variance
CVThe difference between the value of work completed and what it actually cost.
Planned value
PVThe budgeted value of the work that was scheduled to be done by a given date.