What is AC (actual cost)?

    Actual cost is the cost actually incurred for the work performed up to a given date.

    Also written as AC

    AC should cover the same scope and cut-off date as earned value. Including costs for work not yet measured, or leaving out accrued costs, distorts the cost performance index.

    Commitments such as placed orders are not actual cost until the work or goods are received.

    Worked example

    A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). AC is $4.55 million.

    Building better project controls?

    Strataverra is launching first for EPCM projects, shutdowns and turnarounds. Join the early access list for updates, or see where your team stands with the free assessment.