Also written as AC
AC should cover the same scope and cut-off date as earned value. Including costs for work not yet measured, or leaving out accrued costs, distorts the cost performance index.
Commitments such as placed orders are not actual cost until the work or goods are received.
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). AC is $4.55 million.