Plotting planned value, earned value and actual cost on the same S-curve shows schedule and cost performance at a glance: the gaps between the lines are the schedule and cost variances.
Related terms
Planned value
PVThe budgeted value of the work that was scheduled to be done by a given date.
Earned value
EVThe budgeted value of the work actually completed by a given date.
Baseline
An approved snapshot of the schedule, budget or scope, kept so actual performance can be compared against the plan.