Also written as EAC
The simplest formula assumes current cost performance continues. Other methods assume the remaining work goes to budget, or factor in schedule performance as well. No formula replaces a bottom-up re-estimate when the basis of the work has changed.
Comparing EAC with BAC gives the variance at completion: the forecast overrun or underrun.
EAC = BAC ÷ CPI (assuming current cost performance continues)
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). With CPI of 1.055, EAC = $12m ÷ 1.055 ≈ $11.375 million.
Related terms
Estimate to complete
ETCThe forecast cost of the remaining work, from the reporting date to the end.
Variance at completion
VACThe forecast difference between the budget and the final cost.
Cost performance index
CPIShows how much value of work is earned for each dollar spent.
Budget at completion
BACThe total approved budget for the work being measured.