What is EAC (estimate at completion)?

    Estimate at completion is the forecast total cost of the work when it's finished, based on performance so far and what's left to do.

    Also written as EAC

    The simplest formula assumes current cost performance continues. Other methods assume the remaining work goes to budget, or factor in schedule performance as well. No formula replaces a bottom-up re-estimate when the basis of the work has changed.

    Comparing EAC with BAC gives the variance at completion: the forecast overrun or underrun.

    Formula

    EAC = BAC ÷ CPI (assuming current cost performance continues)

    Worked example

    A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). With CPI of 1.055, EAC = $12m ÷ 1.055 ≈ $11.375 million.