Free project controls tools · No sign-up required

    Earned value calculator

    Start with the worked example, then enter your own project figures. Calculate SPI, CPI and cost forecasts, and check what each result means.

    Before you calculate

    1. Choose a reporting date. Use the same project scope, dollar currency and cut-off date for the figures below.
    2. Replace the worked-example amounts with values from your project reports.
    3. Read the results below. SPI is EV ÷ PV: you do not need to enter a detailed schedule, but you must know the planned value by the reporting date. Without a reliable PV, SPI cannot meaningfully assess progress against plan.

    Where to find the values

    BAC · Budget at completion
    Your approved total project budget or cost baseline for the work being measured; check the project cost plan or controls report.
    PV · Planned value
    The budgeted value of work planned by your reporting date; check a time-phased cost baseline, planned-value report or baseline S-curve. The total budget alone is not PV.
    EV · Earned value
    The budgeted value of work actually completed by that date; check a progress or earned-value report based on measured completed work.
    AC · Actual cost
    Costs actually incurred for that work by the same date; check the project cost report, ledger or accounting system. Do not count future commitments as incurred costs.

    SPI is a value-based progress measure, not a measure of critical-path delay or forecast finish date.

    Try the worked example

    Use one dollar currency throughout (for example, AUD or USD). Monetary results use that same currency; indices are currency-independent. Figures stay in your browser.

    Your results

    SPI

    0.92

    Schedule performance index: earned progress compared with planned progress. Below 1 indicates less value earned than planned.

    Attention
    CPI

    1.05

    Cost performance index: earned progress per dollar spent. Below 1 indicates cost overrun.

    On target / favourable
    SV

    -$400,000

    Schedule variance in dollars of planned value, not units of time.

    Attention
    CV

    $250,000

    Cost variance: negative means actual cost exceeds earned value.

    On target / favourable
    EAC

    $11,375,000

    Estimate at completion using the current cost performance index.

    On target / favourable
    ETC

    $6,825,000

    Estimate to complete: forecast remaining cost.

    On target / favourable
    VAC

    $625,000

    Variance at completion: a negative amount forecasts an overrun.

    On target / favourable
    TCPI

    0.97

    Cost performance needed on remaining work to achieve the original budget.

    On target / favourable

    N/A means the relevant divisor is zero or an input is invalid; an infinite result is not meaningful. TCPI is unavailable when BAC does not exceed AC. A positive EAC or ETC is not by itself evidence of being on target.

    Formula reference

    SPI = EV / PV

    Schedule performance index: earned progress compared with planned progress. Below 1 indicates less value earned than planned.

    CPI = EV / AC

    Cost performance index: earned progress per dollar spent. Below 1 indicates cost overrun.

    SV = EV − PV

    Schedule variance in dollars of planned value, not units of time.

    CV = EV − AC

    Cost variance: negative means actual cost exceeds earned value.

    EAC = BAC / CPI

    Estimate at completion using the current cost performance index.

    ETC = EAC − AC

    Estimate to complete: forecast remaining cost.

    VAC = BAC − EAC

    Variance at completion: a negative amount forecasts an overrun.

    TCPI = (BAC − EV) / (BAC − AC)

    Cost performance needed on remaining work to achieve the original budget.