Also written as PV
PV comes from a time-phased baseline: the budget spread over the schedule. Plotted over time, cumulative PV forms the baseline S-curve.
The total budget alone is not PV. Without a reliable spread of budget over time, the schedule performance index has nothing sound to compare against.
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). PV at the reporting date is $5.2 million.
Related terms
Earned value
EVThe budgeted value of the work actually completed by a given date.
Schedule performance index
SPICompares the value of work completed with the value planned.
S-curve
A graph of cumulative cost, hours or progress over time.
Baseline
An approved snapshot of the schedule, budget or scope, kept so actual performance can be compared against the plan.