What is PV (planned value)?

    Planned value is the budgeted value of the work that was scheduled to be done by a given date. It answers "how much should we have achieved by now?".

    Also written as PV

    PV comes from a time-phased baseline: the budget spread over the schedule. Plotted over time, cumulative PV forms the baseline S-curve.

    The total budget alone is not PV. Without a reliable spread of budget over time, the schedule performance index has nothing sound to compare against.

    Worked example

    A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). PV at the reporting date is $5.2 million.