Also written as ETC
ETC is what the project still needs to spend. Comparing it with the remaining budget shows whether the money left is enough.
ETC = EAC − AC
Worked example
A project has a $12 million budget (BAC). At the reporting date, $5.2 million of work was planned (PV), $4.8 million has been earned (EV) and $4.55 million has been spent (AC). ETC = $11.375m − $4.55m = $6.825 million.
Related terms
Estimate at completion
EACThe forecast total cost of the work when it's finished, based on performance so far and what's left to do.
Actual cost
ACThe cost actually incurred for the work performed up to a given date.
To-complete performance index
TCPIThe cost performance the remaining work needs to achieve to finish on budget.